In Fixed Rate mode, the overhead rate is calculated when the project is created and then does not change.
At the moment of creating the project, the total overhead cost for the given month is taken (see the article Overhead Costs) and divided by the sum of the Monthly Workloads of all people (see People -> Total from the column Monthly Workload).
Example:
We have 2 people with a monthly salary, each with 160 hours, totaling 320 hours.
Our overhead costs are $3,200.
Overhead cost per worked hour = Overhead Costs / Sum of Monthly Workloads
Overhead cost per worked hour = $3,200 / 320
Overhead cost per worked hour = $10
An overhead cost (in our case $10) per worked hour is then added to each worked hour—which we can see in the project detail.
Because the overhead cost in the project in Fixed Rate mode is recorded when the project is created and then does not change, several situations can occur that cause inaccuracies.
1. Change in Overhead Costs or Workloads
If, after creating the project, we change the amount of workloads or the amount of overhead costs, this change will not be reflected in the existing projects. Since we usually know the exact amount of overhead only after the end of the month, this inaccuracy will be very common. It is especially noticeable in projects that last several months.
2. Discrepancy Between Tracked Hours and Monthly Workloads
If we stay with the example above and in the given month our two workers do not work exactly 320 hours, but for example only 300 hours, then we will not have all costs allocated in the projects:
Thus, in the projects, we will have overhead costs of $3,000., while the company's total overhead remains $3,200. Therefore, an inaccuracy of $200 arises, making the projects appear more profitable than they actually are.
We can solve the inaccuracies of the fixed rate by using the monthly rate.
When using the monthly rate, the current month is always calculated the same as in Fixed Rate from the start.
However, after the end of the month, the numbers are recalculated according to the actual hours worked.
Let's stay with the example above:
During the month, it will still be calculated as:
Overhead cost per worked hour = Overhead Costs / Sum of Monthly Workloads
Overhead cost per worked hour = $3,200 / 320
Overhead cost per worked hour = $10
After the end of the month, the data is recalculated according to the following formula:
Overhead cost per worked hour = Overhead Costs / Sum of Actually Worked Hours
Overhead cost per worked hour = $3,200 / 300
Overhead cost per worked hour = $10.7
These numbers are automatically allocated to all projects for the given month.
Numbers are also always recalculated if the number of tracked hours changes or if the amount of overhead costs changes.